Thane creek birdge-Three mission in limbo as document caught in Mantralaya Erangal land for afforestation

MUMBAI: Thane creek bridge-Three civil paintings has been no longer began even after acquiring all environmental permissions as Mantralaya but handy over the 1.four hectares of the Erangal land for afforestation to the Maharashtra State Road Development Corporation (MSRDC), which is the nodal company for the mission. The bridge building paintings was once previous anticipated to start in January 2020.

According to a senior MSRDC professional, who didn’t need to be named, advised the Free Press Journal that till the land isn’t formally passed over on papers they can’t continue additional. The authority has additionally written to the state informing that they have got acquired permissions from the Bombay High Court for mangrove chopping aside from having permissions from the Navi Mumbai and Brihanmumbai Municipal companies for chopping of general 333 timber coming within the proposed bridge alignment.

He knowledgeable, “Since the recognized land for mangrove plantation is in Mumbai, the suburban collector has despatched the document for clearance to the state govt. The price of an open plot in Mumbai is costly. While such isn’t the case outdoor Mumbai, the collector typically handover the plot without delay to the MSRDC.”

The MSRDC has recognized Erangal land for plantation of mangrove. A complete of 430 mangroves will likely be reduce for the bridge paintings. The proposed TCB-Three will supply six extra lanes to the present TCB-2. The new creek bridge as soon as able is predicted to strengthen the connectivity between Navi Mumbai and Mumbai, warding off the bottleneck on the current three-lane Thane creek bridge -2, because the current two bridges have been inbuilt 1973 and 1997.

For the Thane Creek bridge-3, the MSRDC has completed the tendering procedure and has appointed Larsen & Toubro Limited (L&T ) for enterprise the civil paintings at price of Rs 775.58 crore in 2017. The decided on corporate has a letter of acceptance and as soon as the land is formally in ownership of the MSRDC then it is going to search the permission from the surroundings division to hold out the paintings within the limited woodland house, stated the professional. 

When puzzled about mission price escalation because the paintings has no longer been began even after two years, the professional defined, “The risk is much less as no paintings has been began. Moreover, as according to coverage, 5 according to cent of the higher mission price can also be thought to be. If the chosen corporate will increase the estimated price greater than that then the quoted price range then the deal must be scrapped for any mission. They might lose the paintings so nobody does that.”